Ongoing notes on Prince2 Manual Chapter 4 - Long story don't ask

Starting up a Project (SU) 4.1 Fundamental Principles

  • Must be a basic business requirement to trigger project. This must be viable.
  • Nothing can be done on project until responsibilities are defined and key roles filled.
  • Base information is needed for rational commissioning of a project.
  • Initiation Stage Plan must be submitted for approval before initiation stage is entered. 4.2 Context This is the first process in PRINCE and project begins once this process is conducted and the Project Board approve commencement of Project Initiation. Leads to Authorising Initiation (DP 1). Project Mandate triggers project usually out of corporate or programme management. May be verbal to complete Project Brief. Assumes information on reason for project already exists. 4.3 Process Description Production of 6 key elements key to process:
  • Design and appointment of project management team.
  • Ensuring information for project brief is available.
  • Establishing the project approach.
  • Establishing the customers quality expectations.
  • Setting up a Risk Log.
  • Creating the Initiation Stage Plan. Objective to enable a controlled start by ensuring:
  • Necessary Project Management Authorities.
  • Sufficient information is available to formalise terms of reference.
  • Appoint individuals to undertake project initiation and key Project Management roles.
  • Project Initiation is planned.
  • Organisation hosting project is informed of its existence and implications. Begins with external definition of problem or opportunity the project must satisfy the Project Mandate. Project Approach explaining way it is intended end products will be produced will help with Initiation Stage Plan. If part of a programme the programme will provide a Project Brief and Project Approach and appoint some or all of the Project Board. Much interplay between assembling project team, agreeing terms of reference and project approach. Target work location is informed and logistical support sorted. 4.3.1 Scalability Various approaches to this proces:
  • Stand alone project, all steps apply.
  • Part of programme then Project Brief or PID passed down, Project Board may be defined, Project Approach and Risk Log controlled at programme level. Just need to check if additional work required.
  • If small project requires less formal handling but should be completed. 4.4 Appointing a Project Board Executive and Project Manager 4.4.1 Fundemental Principles Need decision maker and someone to undertake the project. 4.4.2 Context Must plan initiation before initiation work begins requires appointment of executive and project manager. 4.4.3 Process Description Objectives of process are:
  • Identify Executive from stakeholders.
  • Identify most appropriate Project Manager.
  • Confirm selected peoples availability, acceptance and commitment.
  • Appoint people to respective roles. Requires Project Mandate. Must:
  • Ratify key elements of project mandate.
  • Establish missing information.
  • Identify candidates for Executive and Project Manager.
  • Establish responsibilities of each role.
  • Appoint Executive.
  • Appoint Project Manager.
  • Confirm appointments via agreement to job descriptions by corporate or programme management and appointees. Mandate should indicate type of project, its size and complexity, political and business sensitivity. This will help identify candidates for Project Manager role. May include draft Project Plan. 4.4.4 Responsibilities Corporate or programme management. 4.4.5 Information Needs
  • Project Mandate (Input/Update) Project Trigger
  • Agreed job descriptions for Executive and Project Manager (Output) Basis for sign up by both.
  • Appoint Executive and Project Manager (Output) 4.4.6 Key Criteria
  • If part of programme will programme management team fulfil any roles of project board?
  • Does proposed Executive have financial and functional authority neccesary?
  • Has availability of candidates been measured against forecast duration of project?
  • Are candidates likely to change job? If so has this been taken into consideration?
  • Do appointees have necessary skills and knowledge to undertake tasks? 4.5 Designing a Project Management Team 4.5.1 Fundemental Principles
  • Need right people with authority, reponsibility and knowledge to make timely decisions.
  • Need to reflect interests of all parties involved, business, user and supplier.
  • Requires range of resources and skills must be part of tem.
  • Consider all aspects required, fill all roles identifies in Organisation. 4.5.2 Context Review size and complexity and areas impacted by final outcome. Will overlap with appointing project team. 4.5.3 Process Description Objectives:
  • Design team appropriate to size of project.
  • Identify candidates to produce recommended project team.
  • Determine resposibilites and skills for each role.
  • Where part of programme Project Board may be appointed. Otherwise left to Executive. Organisation and Project Management Team Roles should be used as basis for process. Must:
  • Identify candidates for Project Board and create job descriptions.
  • Assess if Project Board members are likely to delegate assurance roles (allows Project Manager to advise on design of assurance roles).
  • Consider seperate Team Managers are required or Project Manager will fulfill this role.
  • Examine Project Manager role definition and need for support roles.
  • Assign candidate names for all roles. Define if shared, combined roles.
  • Identify who should approve roles. 4.5.4 Responsibilities Joint responsibility of Executive and Project Manager for design. 4.5.5 Information Needs
  • Agreed Executive and Project Manager Job Descriptions (Input) Specifies agreed responsibilities to avoid gaps/overlaps.
  • Project Mandate (Input)