Prince2 Homework - Chapter 15 Plans

Benefits of Plans Identify:

  • If targets are acheivable.
  • Resources needed to achieve targets within timeframe.
  • Activities to ensure quality can be built into products.
  • Problems and risks associated with trying to meet targest and stay within constraints. Other benefits:
  • Avoid muddle and ad hoc decisions.
  • Help management team to think ahead.
  • Yarstick against which progess can be measured.
  • Communication through distribution of plan to all concerned of what is done, allocation of responsibilities and how pogress will be monitored and controlled.
  • Gain commitment from contributors and recipients.
  • Provision of personal targets. Vital to success of the project and must contain sufficient information and detail to confirm targets are achievable. Essential to allocate time to planning activity in initiation stage. Must identify and agree scope of the project, plan in terms of management, resourcing, products, activities, quality and control. Allocate time to refine business case. Also allow time at end of each stage to plan next stage. No plan, no prediction of scope, quality, risk, timescale or cost. Wast time, resource and effort. What is a Plan? Document framed in accordance with predefined scheme or method, describing how, when an by whom a specific target or set of targets is to be achieved. Design of identified targets for products, timescales, costs and quality can be met. Backbone of management information system required fr any project. Must keep in line with Business Case at all times. Reqire approval and commitment from all relevant levels of the project management team e.g. Project Board and Project Manager for Project Plan or Project Manager and Team Manager for Team Plan. What are the elements of a Plan? In PRINCE2 should contain:
  • Products to be produced.
  • Activities needed to create those poducts.
  • Activities to validate quality of the products.
  • Resources and time needed for all activities and need for people with specific skills.
  • Dependencies between activities.
  • External dependencies for delivery of information, products or services.
  • When activities will occur.
  • Points at which progress will be monitored and controlled.
  • Agreed tolerances. Must be endorsed and approved by Project Board. Relates to latest version and plans are presented as management reports. May require summary plans for Board and detailed day-to-day plans. Statement of activities and breakdown of resource requirements must be backed up by text that explains to reader:
  • What plan covers.
  • Intended approach to implement plan.
  • Adhereence t plan to be monitored and controlled.
  • What management reports will be issued.
  • The qiality control methods and resources to be used.
  • Any assumptions upon which the plan is based on.
  • Prerequisites that must be in place on day one of the plan.
  • What risks there are that may prevent plan from being achieved and what measures should be taken to address them. PRINCE2 Approach Allows plans to be broken dowin into loer level plans containing more detail but share same structure an matched back to planned requirements including quality and benefits before approval. Levels of Plan Three levels:
  • Project Plan
  • Stage Plan - may be broken down into a number o team plans.
  • Team Plan Where Stage or Project Plan are forecast to exceed tolerences an Exception Plan will be required. Seldom desirable to plan entire project in detail from the start because:
  • Uncertainty about the detailed nature of later elements of work.
  • Changing and undertain enironment.
  • Risk factors tha could change the situation.
  • Difficulty in predicting the resource availability well into future.
  • Difficulty in predicting business conditions in the future. Detaied plans for forseeable future are however required for control. Project Plan Overview of total project. Part of PID. Only manadatory PRINCE" plan. Provides project costs for Business Case for Project Board to agree to and baseline to monitor actual costs and progress. Identifies key products, resource requirements and total costs. Identifies major control points such as stage boundaries. Project Quality Plan is documented seperately as part of PI> Once PID accepeted project is baselined. Subsequent vversions of Project Plan produced at end of stages reflct:
  • Progress already made
  • Agreed changes in circumstances
  • Revised cost and or duration of total project. Allows Project Board to monitor deviation. If exceeds agreed tolerances must be refferred upwards by Project Boar. Stage Plan Required for each stage. Produced at end of previous stage. Basis of Project Managers day-to-day control May need to be constructed form specalis development plans. More detaied than project plan. Reasess validity of assumptions and risk analyses. Confidence in stage plans because:
  • Planned close to time events will take place.
  • Shorter duration.
  • Developed with knowledge of performance of earlier stages. Team Plan Optional will be determined by size and complexity of job. Needed if several different skill teams. Parralell to stage plans. Should contain Quality Plan/ User and Supplier Proect Assurance will have input:
  • Identifying products of key interest to their role.
  • Specifying who should be quality checking producs.
  • Specifying points at hich quality checking should be done. Exception Plan Only use if tolerences exceeded to replace existing plan. At level of detail of plan it replaces. Needs appropriate approval, Stage Plan/Project Board, Project Plan/Programme Corporate Management.