Purpose of Control
Control is all about the decision making process in PRINCE. It exists to ensure the project is:
Producing required products that meet pre-defined quality standards.
Is carried out on schedule in accordance with resource and cost plans.
Remains viable against business case.
Controls ensure that for each level of the Project Management Team the next level up can:
Monitor progress.
Compare acheivement wth plan.
Review plans and options against future situations.
Detect problems.
Initiate corrective action.
Authorise further work.
Must also cover capturing information on changes outside the project and taking neccessary actions.
Controls Overview
Many controls in PRINCE" are event driven including all decision-making ones. Examples are End of Stage, completion of the Project Initiation Document, the creation of an Exception Plan. Some time driven controls like reguar progress feedback. Project Level has overall control from the Project Board recieving information form the Project Manager and Project Assurance. They control if the project continues, stops or changes direction or scope.
Applies concept of management by exception where the Project Board are concerned. kept informed by reports during the stage. Major controls they have are:
Project Initiation (Should project be undertaken?)
End Stage Assessment (Has stage been successful? Is prject still on course? Is business case still viabel? Are risks controlled? Should next stage be undertaken?)
Highlight Reports (regular progress report during stage).
Exception Reports (PB considers action to take when Excetion occurs and recieves early warning of deviation)
Exception Assessment (PB meet to review and approve Exception Plans).
Project closure (has project delivered all expected? Are any follow-on actions needed? What lessons have been learned?)
Must also montor external environment and bring to attention of those concerned including the Project Manager changes that could impact the project.
Project Manager controls day-to-day within a stage and can make adjustments within tolerances defined by the Project Board and they do not effect the Business Case. Work Package auhtorisation is the control the Project Manager uses to allocate work. Includes controls on uality, time, cost and identifies reporting and hand-over requirements.
Planned acievement includes required quality of products. Aim to detect poblems early and rectify.
Progress monitored against plans with control actions if adjustments required.
Controlled Close ensures no drift on beyond life of project and ensure Project Manager satisfies the Project Board objetives in the PID have been met.
Project start-up
Important pre-requisite of project control. Project Start-up ensures:
Set up Project Management Team so that Project Board and Project Manager can make initial decisions about project.
Develop what may be rudimentary Project Mandate into Project Brief.
Plan the initiation stage.
Likely to be sort stage but approval of Project Board is required before it can be done. Must therefore create plan for initiation stage that the Project Board can examine to understand commitment more clearly. This plan should include statement of any controls to be applied and reports Project Bard is to receive.
As creation of Project Mandate is outside control of the project it gets fleshed out into Project Bief.
Authorising Initiation DP1
After SU Starting a Project Project Board approves progress to initiation stage which officially starts the poject. May be done with or without formal meeting. Once authoriesed a copy of the Project Brief should be sent to all stakeholders including group responsible for operational support of final prduct.
Project Initiation
Ensures before significant resource is spent that everyting in the project is agreed:
Project ojectives?
What products will be delivered?
Reasons for proect?
Who the Customer is?
Who has which responsibilities and authority?
Project boundaries and interfaces to the outside world?
How objectives will be met?
What assumptions have or can be made?
What major risks exist that may prevent project from meeting objectives?
When major products will be delivered?
How much the project will cost?
How project will be controlled?
Division of project into stages?
How acceptabilty of products will be assessed?
These are answers are addessed in the Project Initiation Document. Main product from this stage. Also produced is next stage plan so project can begin without delay if PID is accepted.
PID is frozen once accepted. Now baseline document agianst which project can be measured. Allows checks that changes were undertaken in a controlled way. Parts of the PID though are active and volatile:
Project Plan.
Business Case.
Risk Log.
Kept in management portion of filing system.
Stage Selection
Project Board approves break down of projects into stages. End of stage is manjo control point.
Communication Plan
Identifies who needs to give and receive information about project. Shows:
Who needs information.
What information they need.
When they need it.
Format it should be presented.
Should include senior or programme management, stakeholders and other interested parties.
Controlled Progress
Needed to ensure project stays in linewith expectations defined by PID and Stage Plan.
Tolerance
Tolerance is permissible deviation from plan without taking deviation to the attention of the next higher authority.
Tolerances are handed downwards and where exceeded exceptions handed upwards.
Tolerances are: Time, Cost, Scope, Risk, Quality, Benefit.
Contingency and change budgets exist to meet plans for linked risks and to prevent tolerence being used to cope with change.
Product Descriptions
Ensure people know:
Whay it is needed.
What it will look like.
Sources it will be derived from.
Quality specification to which it will be built.
Product Description is a control document written as part of the planning process. Defines product and standards to ensure it is fit for purpose.
Should be drafted when product identified in a Product Breakdown Structure during the planning process. Must be approved by the Project Board as part of the Project Assuarce role. Form part of Work Packages given to suppliers.
Work Package
Trigger from Project Manager to individual or group to undertake work during a stage. Undertaken in Authorising Work Package (CS1) and accepted by producer in Accepting a Work Package (MP1). Defines product and constraints such as time and cost.
Quality Control
PRINCE2 does not define all quality procedures and techniques but does include Quality Check a team method especially useful in checking the quality of documents.
All quality checks should be recorded along with results in the quality log.
More follows sleep pause in proceedings.....