3.1 Management Levels
4 parallel management levels:
Coporate or programme management is ighest level, outside Project Management it sets the agenda.
Directing a Project highest level wthin project completed by Project Board. For key decision making and direction setting.
Managing a project- day-to-day planning and control level, largely handled by the project manager.
Managing product delivery, hadled by Team Managers.
Interact:
Higher level processes control lower levels e.g. managing a project creates work package for managing product delivery.
Output at lower levels provides inputs that allow higher-level processes to function effectively.