Key questions:
What are we trying to do?
When will we start?
What do we need?
Can we do it alone or do we need help?
How long will it take?
How much will it cost?
Structured project management gives logical, organised famework following deined steps to identify answers to these questions.
Prince2 states a project should have:
An organised and controlled start (plan and prepare properly before begining project)
An organised and controlled middle (once started keep it on track)
An organised and controlled end (once done, tidy up loose ends)
Project manager responsible for the organising and controlling. Will select people to work on the project and be responsible for making sure the work is done on time and properly. Draws up the project plans that describe what the poject team will be doing and when they expect to finish.
Customer/Executive is the person paying for the project. The person who will use the results or imapacted by the outcome is the user. These two may be synonymous in many projects.
Person who provides expertise to do the actual work on the project is the supplier or specialist.
All need to be co-ordinated so required outcomes are delivered on budget, on time and to the required quality.
Each Prince2 project will have a Project Board made up of customer, user representative and specialist. Customer, Senior User and Senior Supplier respectively. Project Manager reports regularly to the project board. This board is responsible for providing necessary decisions for project to proceed or overcome difficulties.
Project Assurance provides independent view of project progress and consists of business, user and specialist viewpoint. Ensures project is viable in terms of costs, beniefits, meeting user requirement and suitable solution is being delivered. Maybe undertaken by project board or seperate group.
Aministrative work often completed by Project Managers to sort meetings etc and keep all on track.
Method also explains how to manage risk (identify risks and positive or negative impact), quality and control change (preventing change taking project off in wrong direction as people change their minds).
Prince2 delivers set of processes to work through to give framework to gather relevant information. Can't deliver project for you.