Project Team Roles
Project Board
Approves major plans and authorises major deviations from agreed stage plans. Authority that signs off each stage and authorises next stage. Ensures required resources and arbitrates conflict or negotiates solutions between project and external bodies. Approves appointment and responsibilities of the Project Manager.
Has following responsibilities that need tailoring project by project:
Approves start of project by accepting Project Brief.
Agrees with Project Manager their responsibilities and objectives.
Confirms with corporate or pogramme management of project tolerences.
Specification of external constraints on project such as quality assurance.
Approval of accurate and satisfactry Project Initiation Document including that it complies with customer standards and policies and associated contracts with suppliers.
Delegation of Project Assurance roles.
Commitment of project resources required by next stage plan.
As project progresses:
Provision of guidance and direction to project ensuring stays within specified constraints.
Review completed stages and approve next stage plan.
Review and approve stage plans and any exception plans.
Ownership of identified risks as allocated at plan approval time - monitors risk and advises Project Manager of changes in status and actions to take to reduce risk.
Approval of changes.
Compliance with corporate or management directives.
At the end of the project:
Assurance all produces have been delivered satisfactorily.
Assurance acceptance criteria have been met.
Approval of nd Project Report.
Approval of Lessons Learned Report and passage to appropriate standards group to ensure action.
Decisions on recommendations for folow on actions and passage of these to appropriate authorities.
Approval where apropriate of Post-Project Review Plan.
Project Closure Notificaton to corporate or progamme management.
Project Board owns the process Directing a Project DP
Ultimately responsible for assuarance that project remains on course to deliver desired outcome of required quality to meet business case defined in PID.
Approves and funds changes.
Executive
Has ultimate responsibility for the project supported by Senior Uer and Senior Supplier. Role is to ensure focus on objectives and delivering product achieving projected benefits. Executive ensures value-for-money balancing demans of business, user and supplier.
Oversee development of Project Brief and Business Case
Ensures coherent project organisation and logical set of plans.
Authorises customer expenditure and set stage tolerances.
Monitor control the progress of project at strategic level, in particular reviewing the Business Case continually.
Ensure proposed changes of scope, cost, timescale checked against possile effects on Business Case.
Ensure risks are tracked and mitigated against.
Brief corporate or programme management on project progress.
Organise and chair Project Board meetings.
Recommend future actions on project to coroporate or programme management if project tolerence exceeded.
Approve end project Report and Lessons Learned Report ensure outstanding issues are documented and passed on to appropriate body.
Approve sending of project closure to programme or corporate management.
Ensure benefits are realised by holding post-project review and forward to review to appropriate stakeholders.
Executive responsible for overall business assurance ensuring it stays on target to deliver benefits on schedule within tolerances for budget and schedule.
Business assurance covers:
Validation and monitring of Business Case against external events and against project progress.
Keeping project in line with customer strategies.
Monitoring project finance on behalf of the customer.
Monitoring business risks to ensure that these are kept under control.
Monitor supplier and contractor payments.
Monitor changes to Project Plan for impact on Business Case or needs of Business.
Assessing impact of potential changes on Business Case or Project Plan.
Constraining user and supplier excesses.
Informing project of changes caused by programme of which it is part.
Monitoring stage and project progress against agreed tolerances.
Executive is key decision maker with advice and commitment from others.
Senior User
Responsible for the specification of te needs of all those who will use the final product, for user liaison with the project team and monitoring the solution meets needs of the Business Case in terms of quality, functionality and ease of use.
Represents users to whom product will deliver benefits. Commits user resources aainst requirements. May require more than one person to cover user interests. Shouldn't be too split it isn't effective.
Specific Responsibilities are:
Ensure desired poject outcome is achieved.
Progress towad outcome required by users remains onsistent from user perspective.
Promote and maintain focus on desired project outcome.
Ensure user resources required by project are released.
Approve Product Descriptions for products that act as inputs or outputs from supplier function or that will directly affect them.
Ensure products are signed off once completed.
Prioritise and contribute user opinions on Project Board decisions on whether to implement recommended changes.
Resolve user requirements and prioity conflicts
Provide user view on Follow-on Action Reccomendations.
Brief and advise user management on all matters concerning project.
Assurance responsibilities are:
Specification of users needs is accurate, complete and unambiguous.
Development of solution at all stages is monitored to meet users needs and progress towrds that.
Impact of potential changes is evaluated from user point of view.
Risks to users are constantly monitored.
Quality checking of product has appropriate user representation.
Quality control procedres are used correctly to ensure product meets user requirements.
User liaison is functioning effectively.
May delegate authority for som assurance responsibilities.
Senior Supplier
Represents interests of those designing, developing, facilitating, procuring, implementing and possiby operating or maintaining products. accountable for quality of prducts delivered by the supplier. Must have authority to commit or aquire supplier resources
In some environments customer may share design authority or have major say in it.
May require more than one person to represent suppliers.
Specific responsibilities:
Agree objectives for supplier activity.
Make sure progress towards outcomes is consistent from supplier point of view.
Promote and maintain focus on project outcome from supplier management perspective.
Ensure supplier resurces required for project are made available.
Approve Product Descriptions for supplier products
Contribute supplier opinions on Project Board decisions ot implement recommendations on proposed changes.
Resolve supplier requirements on priority conflicts.
Arbitrate on an resolve supplier priority or resource conflicts.
Brief non-technical management on supplier aspects of project.
Responsible for specialist integrity of project. Assurance responsibilities are.
Advise on selection of development strategy, design and methods.
Ensure any supplier and operating standards defined by project are met and used to good effect.
Monitor potential change and impact on correctness, completeness and integrity of products against Product Description from supplier perspective.
Monitor risks in production aspects of project.
Ensure correct use of quality controm procedures so product adheres to requirements.
May delegate some assurance responsibility.
Project Manager
Has authoity to run project on day-to-day basis on behalf of the Project Board within constraints laid down by the board.
Prime responsbility to ensure project prduces required products o required standard of quality within specified constraints of time and cost. Responsible for producing result capable of achieving benefits defined in business case.
Specific responsibilities:
Manage production of required prducts.
Direct and motivate project team.
Plan and monitor project.
Agree delegation and use of Project Assurance roles required by Project Board.
Produce PID.
Prepare Project, Stage and if neccesary Exception Plans in conjunction with Team Managers and appointed Projecte Assurance and agree them with Projct Board.
Manage risks, including development of contingency plans.
Liaise with programme management if project part of programme.
Liaise with programme management or related projects to ensure no overlooked or duplicated work.
Responsible for overall progress and use of resources and initiate corrective action if needed.
Responsible for change control and required configuration management.
Prepare and report to Project Board through Highlight Reports and End Stage Reports.
Liasie with Project Board or appointed Project Assurance on overall direction and integrity of project.
Agree technical and quality strategy with appropriate members of project board.
Prepare lessons learned Report.
Prepare any Follow on-Action Recommendations Report.
Prepare End Project Report.
Identify and obtain any support or advice required for managment, planning and control of project.
Be resopnsible for project admin.
Liaise with suppliers or account managers.
May also perform Team Manager and Project Support roles.
Team Manager
Prime responsbility t ensure prodution of products defined by Project Manager to appropriate quality in timescale and at cost acceptable to Project Board. Reports to and takes direction from Project Manager.
Specific responsibilities.
Prepare plans for teams work and agree with Project Manager.
Recieve authorisation fro Project Manager to create products.
Manage the team.
Direct, motivate, plan and monitor teams work.
Take repsonsibility for progess of team's work and use of team resources and initieate corrective action within constraints aid down by Project Manager.
Advise Project Manager of deviations from plan, reccomend action, help prepare Exception plans.
Pass back to Project Manager products completed and approved in line with Work Package Plan.
Ensure project issues reported to person maintaining Issue Log.
Ensure evaluation of any Project Issues that arise in teams work and recommend actions to Project Manager.
Liaise with any Project Assurance roles.
Attend stage assessments as directed by Project Manager.
Arrange with lead team checkpoint meetings and produce Checpoint Reports aas agreed with Project Manager.
Ensure quality controls of team's work are planned and perfored correctly.
Ensure appropriate entries in Quality Log.
Maintain and ensure existence of team files.
Identify and advise roject Manager of risks associated with Work Package.
Ensure all identified risks are entered in risk log.
Manage specif risks as directed by Project Manager.
Project Assurance
Covers all interests in project, business, user, supplier.
Must be independent of Project Manager, Project Board can not delegate responsibilities in this area to Project Manager.
Specific responsibilities need to answer the question What is to be assured, may include:
Maintainence of thorough liaison throughout project netween supplier and customer.
User needs and expectations are met and managed.
Risks are controlled.
Adherence to business case.
Constant reassessment of value-for-money.
Fit with overall strategy of corporation or programme.
Right people are being involved.
Acceptable solution is being developed.
Project remains viable.
Scope of project is not 'creeping upwards' unnnoticed.
Focus on business need.
Internal and external communications are working.
Applicable standards are being used.
Legislative containts are observed.
Needs of specialist interests (eg. security) are being observed.
Adherence to quality assurance standards.
Need to check all standards are met don't assume they will be.